Path at Megan Green


Event Details

This event finished on 25 January 2023


Further work for West End Parks department extending the path work we started last July. (Ben and his digger confirmed) One of Barry’s venues.

Just our luck! Last year the ground was hard from prolonged dry weather.  This time its going to be hard again after prolonged rain and hard frost.

Please bring a wheelbarrow if you can.

Week 1. Cracking pace, despite the frozen ground. 39m completed.

Frosty morning at Megan Green. All hard at work. January 2023.

Hard work assisted by Ben’s mechanical muscle.

Wet hoggin was too soft to whack flat. 42m of path dug out and layed.

Week 2 27m done and the scalpins ran out.

We’d have done more but the scalpins ran out.