Two weeks for West End Parish Council extending the path across Megan Green.  Baz to lead. We may finish this task after making progress over 6 previous days.

July 2022 the ground was baked hard. January 2023 it was frozen solid. Let’s hope it’s just right this April. But it looks like it will be very soft!

Everyone park on the road, the grass is too soft to drive on. Please bring your favorite shovel or spade. Ben and his digger will not be with us.

Week 1 photos, 36m done, with time to spare.

Preparation of the route.

Megan Green, 36m laid.

 

Megan Green, centre of map, 140 years ago.

Week 2. Another 26m added to complete this path. A total of 320m.

Megan Green. Long path complete.